Sprints:Sprint3

Jeff Lindsay edited this page Feb 13, 2017 · 3 revisions

Retrospective

(done late, the following monday)

What went well

  • Got a lot done
  • Roughly under budgeted time
  • Started to get help
  • We did get a bunch of people requesting access
  • Tracking stalled
  • Tracking unplanned without issues (as notes)
  • Extra time let us explore CI optimizations, etc
  • Feedback from users! Auto-deploy will only make that tighter

What could have been better

  • Communicating days off (calendar in place)
  • Stalled/Todo left from poor planning (dependencies, estimations)
  • Design prototypes/spikes need to be REALLY well defined to delegate

Next Sprint

  • Open issues for ad-hoc tasks
  • Plan for 7 days of planned, 2 days unplanned/buffer, 1 day buffer/planning
  • Try new column for issues created but not acted on: Future

Other notes

  • Doc gen + manual docs led to redesign metacommands
  • Further validation Cobra might not be best