Attendees: Mehad, Fahim, Domenic, Lynn, Shawinder
Date: Sept 19, 2024
- Members produced requirements for the component of the project they were in charge of.
- Members conducted requirement validation as a group.
- Members produced non-functional requirements
- Members conducted non-functional requirements validation as a group.
- Shawi: Gain an understanding of system tray applications and produce a prototype using visual studio.
- Mehad: Produce an app prototype and implement server client communication prototype.
- Domenic & Fahim: Implement backend code required to detect display information.
- Lynn: Implement functionality to detect audio output devices from the host PC.
Attendees: Mehad, Fahim, Domenic, Lynn, Shawinder
Date: Sept 26, 2024
- Members collaborated on assignment 3 and produced a usecase diagram for DAIRemote.
- Members distributed which story to work on for parts 2 & 3 according to member roles.
- Members discussed current progress on sprint 1 features and planning for sprint 1 demo.
Attendees: Mehad, Fahim, Domenic, Lynn, Shawinder
Date: Sept 29, 2024
- Discussed plan for how Sprint 1 presentation will go (what has been done and order of presenters)
Attendees: Mehad, Fahim, Domenic, Lynn, Shawinder
Date: Oct 17, 2024
- Shawi: Working on system tray icon and continue doing that for more functionality
- Mehad: Completed client broadcast search for host & connection. Next steps: creating interactive tutorial for Android app.
- Lynn: Worked on audio output switching. Next steps: implement hotkey for audio output switching using SoundSwitch
- Domenic: Worked on delete display profile function in backend and looked into possible UI changes.
- Fahim: Completed implementation of server client communication backend.
- Shawi: System tray icon
- Mehad: Client broadcast search for host.
- Lynn: Display audio output options.
- Domenic: Saving display profiles.
- Fahim: Communication server backend.
Attendees: Mehad, Fahim, Domenic, Lynn, Shawinder
Date: Oct 24, 2024
- Discussed Sprint 2 progress and how Presentation 3 will go.
- Shawi: Completed system tray
- Mehad: Finished implementing interactive tutorial for Android application
- Lynn: Worked with soundswitch instead of naudio
- Domenic: Worked on changing and fixing implementation of load and delete functions in desktop application UI.
- Fahim: Sprint 2 goals met.
- Shawi: Work on UI or help with switching audio devices
- Mehad: Work on implementing functionality to allow the user to directly input the ip address.
- Lynn: Continue working on switching between audio devices
- Domenic: Work on redesigning the UI and correctly implementing the load and delete functions on the desktop application.
- Fahim: Review implementation of sprint 2 goals to find room for improvement.
Attendees: Mehad, Fahim, Domenic, Lynn, Shawinder
Date: Nov 22, 2024
- Discussed near-finished progress on Assignment 5 individual unit tests, and worked on Assignment 6 together